Across the industry there are long lead times for networking and some server chipsets. We are currently seeing wired switches with lead times between 5 and 9 months and WiFi access points between 3 and 6 months.
Server and storage hardware is less constrained with around 2-4 months generally being seen.
This is due to the ongoing shortages in chip manufacturing with some manufacturers now being fully booked into 2023. Given these constraints we are advising customers to look up to 12 months ahead